Molten salt pump installation precautions
1. Have good ventilation, to ensure that the motor and the molten salt pump fully heat.
2. The opening size of the mounting plate for the molten salt tank (tank) should be greater than or equal to the minimum body size of the molten salt pump as indicated on the installation dimension drawing.
3. The outlet flange of the molten salt pump is not allowed to withstand the external force and external torque, otherwise it may lead to different parts of the molten salt pump rotating parts and fixed parts affect the reliability and life of the pump or lead to molten salt pump can not operate normally, often cause:
A molten salt pump vibration than normal;
B rotor is difficult to rotate the rotor by hand.
Therefore, the external piping system should be installed on the molten salt flange of the liquid outlet of the molten salt pump, and the liquid outlet pipe set screw on the pump base can not be adjusted freely.
4. Bearing bracket and bracket jacket cooling water pipes should be connected in parallel.
5. Molten salt pump to install ammeter to monitor pump operation.